It was learned on May 22 that after Changzhou made the rail transit network plan in 2005, the revision of the plan was initiated in 2012, which includes a long-term plan to 2030. In 2030, the rail transit network of Changzhou will cover both the central urban area and the suburb areas. The central rail transit contains six lines with total length of 208 km, including 182 km underground and about 26 km of elevated light rail transit. The six rail transit lines in planning are: Number Start from Destination Length Line 1 Xingang Center West Taihu Lake 42km Line 2 Hengshanqiao Benniu 36km Line 3 Changzhou North Station Miaoqiao 29km Line 4 Xinlong Center Jianhu 36km Line 5 Qinglong Science & Education Town 28km Line 6 Xuejia Science & Education Town 37km